1. Prepare four 10AWG wires to crimp RNB5-3.7 copper terminals at both ends for grounding connection of battery module.
2. Use four grounding wires to connect the battery module with the master control from positions 1-2, 2-3, 3-4 and 4-5 when user install the fixed strips.
3. Connect the inverter with a ground wire at position 6.
Please look at the diagram attached to see it visually.